Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the js_composer domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /nas/content/live/jefuller/wp-includes/functions.php on line 6121
Lynx Lake • JE Fuller

Lynx Lake

Project Highlight: AGFD – Willow Spring Phs III

Location

Yavapai County, AZ

Client

Arizona Game and Fish Department

Project Leads

Ethan Rode
Tyler Azeltine
Scott Ogden
Brian Iserman
Jeffrey Despain

Problem

  • The new principle outlet needed hydraulic controls.
  • The lake could not be drained.
  • The old controls were manual

Approach

  • Hydraulic controls were designed and would be installed.
  • Divers were hired to do the underwater work.

Solution

  • The new hydraulic ram was installed.
  • The new hydraulic controls and lines were installed.
  • A protective cover and actuator house were installed.